Drive By 8-30-25

Image
 Drove by the property today, took a few pictures.  Coming along pretty nicely. More of the roof sheeting installed (carport is now covered). More of the inside framing done, showing the pantry and great room. Great room, kitchen overhang and  Great room and stairwell to the garage. Master Bedroom with closet,  Kitchen area Windows have arrived waiting to be installed. Working on the carport.  structural members are in Back of the house, some unfinished roof sheeting sticking out. Inside corner of the carport.  Expansion joints on the carport as the house settles. Another picture showing the expansion joint on the carport. More details on the structural on the carport. More details on the structural on the carport. Ceiling joists for the crawlspace above the bedrooms More ceiling Joists for the crawlspace above the bedrooms. More ceiling Joists for the crawlspace above the bedrooms. More ceiling Joists for the crawlspace above the bedrooms. More ceiling Joi...

Drive By 8-27-25

Image
 My Wife Drove by the property on Wednesday and took these pictures. Street view, all the roof joists are in place and they started putting up the roof sheetings. Stated putting up the support for the car port extension, some of the roof sheeting is vissible. View from the other side of the house showing the scaffolding to get the roof sheeting up there.

Builder Update 8/14/25

Image
 Not to much progress this week. but a little more was done. More of the roof structure is going up.  The right roof overhand framing is in. More details of the roof structure. Scaffolding on the right side of the house to work on the roofing. Right side of the house, view from the back side (looking towards the street). Back of the house, some of the roof overhang is up. More pics from back of the house, showing the roof overhang. Left side of the house, showing the roofing overhand, and the overhang for the carport. Close up view of the roof structure, left back corner. Front right corner of the house. Left front corner, overhand for the carport. Left side of the house, the big forklift in the future carport.

Drive By 8-9-25

Image
 We drove by the property, and dropped off some plumbing items.  We walk around admiring the work done so far. Top of stairs looking towards the front of the house.  Temporary support to install the roof joists in way of the stairs. Great Room, looking towards the kitchen, framing for the bedrooms, bathroom, laundry, and pantry are up.  Temporary support for the Center Roof beam, will be removed at some point in the future. Great Room, looking towards the top landing of the stairs.  Temporary support for the pony wall and temporary access for roof joists in the stair well, to be removed at some point during construction. Admiring the Center Roof Support and structural members. Hallow wall, originally intended to install Murphy bed in this cubby. will have to bring up this issues with the builder. Garage, workshop #1 (left) and Workshop #2 (Right) Back left corner.  Workshop #1 window (Below), Second Bedroom Window (Above) Carport Roof, structural support fo...